A Detailed Engineering Assessment (DEA) tells you what an existing building can safely carry. It is the document buyers, the RSC, banks and authorities ask for, and it is the starting point for any strengthening work. The first question owners ask is almost always the same: what will it cost?
This guide gives the price ranges used in Bangladesh's industrial sector in 2026, shows how the fee is worked out with real numbers, and explains what makes one building cost more than another.
How the fee is calculated
Consultants price a DEA on the total floor area, not the plot or the footprint. Add every floor together. For a building with the same floor plate on every level:
Total floor area = ground-floor area x number of floors
The fee then has two parts:
- A fixed part for the work that is much the same on any building: mobilising the team and testing equipment, transport, field data, sample collection, laboratory tests, setting up the analysis model and writing the report.
- A rate per square foot for the survey, testing and checking that grows with the building. The rate falls as the building gets bigger: the first 50,000 sq ft cost more per sq ft than the next 100,000, and those more than the rest.
The purpose of the DEA then adjusts the total: buyer and RSC assessments cost about a third more, a RAJUK notice or an extension a little more.
How a DEA fee is built
Four buildings, from small to very large: watch the fixed part stay put while the cost per square foot falls.
Worked examples
| Building (Gazipur or Narayanganj) | Total floor area | General DEA | Buyer or RSC DEA |
|---|---|---|---|
| Small 2-storey workshop, 6,000 sq ft per floor | 12,000 sq ft | About Tk 3.0 lakh (minimum) | About Tk 4.1 lakh |
| Garment factory, 20,000 sq ft per floor, 5 floors | 100,000 sq ft | About Tk 4.7 lakh | About Tk 6.3 lakh |
| Factory, 50,000 sq ft per floor, 5 floors | 250,000 sq ft | About Tk 7.1 lakh | About Tk 9.6 lakh |
| Large complex, 100,000 sq ft per floor, 5 floors | 500,000 sq ft | About Tk 10.6 lakh | About Tk 14.3 lakh |
These are first budgets for 2026, before VAT; each is likely within about 6% either way. Sites outside Dhaka division add travel. A written quote follows a look at the building and its documents.
Why there is a minimum fee
Some parts of a DEA cost almost the same whatever the size of the building: mobilising the survey team and testing equipment, setting up the analysis model, checking the foundations and soil information, writing and reviewing the report. On a small building the per-square-foot rate does not cover that fixed work, so consultants set a floor. In 2026 a complete DEA is rarely done for less than about Tk 3 lakh, or about Tk 4 lakh for buyer or RSC work.
What moves the fee up or down
| Factor | Lower fee | Higher fee |
|---|---|---|
| Drawings | Reliable structural drawings exist | No drawings: a full as-built survey is needed |
| Structure | Regular grid, repeated floors | Irregular layout, extensions, mixed RCC and steel |
| Testing | Uniform concrete, standard sampling | Wide variation, so more cores and NDT locations |
| Soil information | A reliable soil report exists | New boreholes needed |
| Access | Free access during the day | Work around production, at night or on holidays |
| Location | Dhaka, Gazipur, Narayanganj | Remote districts, with travel and stay |
What a complete DEA quote should include
- As-built survey: grids, member sizes, slab thicknesses, storey heights, and as-built drawings if none exist.
- Material testing: a stated number of concrete cores, plus rebound hammer, ultrasonic pulse velocity and ferro-scan readings. See what concrete tests cost.
- Load survey: machinery, storage, generators and water tanks as they are today.
- Foundation and soil review, and whether new boreholes are included.
- 3D analysis to BNBC 2020, with every member checked.
- Report in the format your buyer, auditor or authority needs, with a corrective action plan and strengthening options.
If a quote does not say how many cores and test locations it includes, ask before you sign. That number is the biggest difference between a cheap DEA and a reliable one.
Costs that are usually separate
- New soil investigation. Boreholes are billed separately when no reliable soil report exists, usually at least three per site. See our testing price list.
- Extra testing beyond the agreed plan, if early results show wide variation.
- Strengthening design. If the DEA finds deficiencies, the retrofit design is a separate stage. See what retrofitting costs.
- VAT and tax. Check whether a quote includes VAT and AIT.
How long it takes
A mid-sized factory usually takes 4 to 8 weeks from site survey to final report; laboratory results for cores are often the longest step. More in how long a DEA takes.
Comparing DEA quotes
- Put the quotes side by side on the same items: number of cores, NDT locations, soil work, report format and timeline.
- Ask who reviews the analysis. A second engineer checking the calculations is good practice.
- Ask for a sample report table of contents, with client details removed.
- Be careful with a quote far below the figures above: something, usually testing, has been left out.
Getting a quote
Send us the ground-floor area, number of floors, building use, location and any drawings you have. We reply with a written, itemised fee and testing plan. Ask for a DEA quote.
Topics:DEAcostdetailed engineering assessmentfactoryBangladesh
Frequently asked questions
How much does a DEA cost per square foot in Bangladesh?
It depends on size, because part of the fee is fixed. In 2026 a 100,000 sq ft factory works out at about Tk 4.7 per sq ft, a 250,000 sq ft factory about Tk 2.8 and a 10,000 sq ft building about Tk 30, because the minimum fee applies. Buyer and RSC work costs about a third more.
What is the minimum fee for a DEA?
About Tk 3 lakh for a general assessment and about Tk 4 lakh for buyer or RSC work. Testing, transport, field data, samples, lab work and the report cost much the same on a small building as on a large one.
How is the floor area for a DEA calculated?
Add up all floors. For a building of the same size on every floor, multiply the ground-floor area by the number of floors: 20,000 sq ft x 5 floors = 100,000 sq ft.
Does the DEA fee include laboratory tests?
Usually the main tests are included, but the number of cores and NDT readings varies between quotes. Ask each consultant how many cores, rebound hammer and ferro-scan locations are included, and how extra tests are charged.
Why do DEA quotes differ so much?
Mostly because of testing. A very cheap quote often means fewer cores and readings, which makes the conclusions less reliable and can lead to buyers or auditors asking for more work later.
About Muhammad Sarowar Hossain
Founder & CEO, Prime Base Engineering, B.Sc. in Civil Engineering, PGDSCM-ISCEA. Muhammad Sarowar Hossain founded Prime Base Engineering and leads its structural assessment, retrofitting and construction work. He has worked on structural retrofitting of factories and industrial buildings across Bangladesh since 2017.