Retrofitting cost calculator for Bangladesh
A member-by-member budget for strengthening an existing building: choose the parts, the method, the floor height and how much of the structure needs work.
Most likely budget
৳ 2.11 crore
Likely between ৳ 1.96 – 2.25 crore · Total floor area: 1,00,000 sq ft
A guide only, not an exact quote.
Counted: about 51 columns and 88 beams per floor (a column every 7 m), 1 floor strengthened.
Plus the assessment that designs it: ≈ ৳ 4.7 lakh
- Strengthening works68%
- Surface preparation and making good20%
- Propping and temporary works12%
Indicative only, excluding VAT. Strengthening is priced item by item from a BOQ of the design; the assessment comes first.
Typical retrofitting budgets in 2026
| Project | Total floor area | Per sq ft | Most likely budget |
|---|---|---|---|
| Factory, 20,000 sq ft per floor: ground-floor column jackets | 1,00,000 sq ft | ৳ 99 | ৳ 98.5 lakh |
| Same factory: columns and footings | 1,00,000 sq ft | ৳ 211 | ৳ 2.11 crore |
| Same factory: columns, footings and beams | 1,00,000 sq ft | ৳ 328 | ৳ 3.28 crore |
| Same factory: selected members on every floor | 1,00,000 sq ft | ৳ 549 | ৳ 5.49 crore |
| Apartment, 4,000 sq ft per floor, six floors: CFRP on ground-floor columns | 24,000 sq ft | ৳ 138 | ৳ 33.2 lakh |
A guide only, not an exact quote. 2026 rates; VAT and AIT extra.
What changes a retrofitting budget
- Which parts
- Columns are priced per metre of height, beams per metre of span, footings per column and slabs per sq ft of panel. Footing blocks are often the largest single item.
- Method
- RC jacketing is the usual choice; steel jacketing is about 15% more and faster; CFRP is about 45% more but adds almost no size or weight.
- Floor height
- Factory floors of 14 to 20 ft need longer column jackets than 10 to 12 ft office floors.
- Working in a running building
- Phasing, propping and night shifts in an occupied factory add time and temporary works; the split under the figure shows their share.
Questions owners ask
How much does retrofitting cost per column in Bangladesh?
An RC column jacket costs about Tk 42,000 per metre of height including rod and cement, so a 4.6 m (15 ft) factory column is about Tk 1.9 lakh. A punching-shear block on its footing adds about Tk 2.2 lakh.
Is retrofitting cheaper than rebuilding?
Usually yes: strengthening the members that need it costs a fraction of a new building, and the building can often stay in use while the work is done in phases.
Do I need a DEA before retrofitting?
Yes. The assessment finds which members are weak and the design says how to strengthen them; the calculator shows the assessment fee under the figure.
Which is better, RC, steel or CFRP jacketing?
It depends on the load, the space and the time you have. RC is the most common and cheapest; steel is quicker; CFRP suits tight spaces and buildings that cannot take extra weight. The design engineer decides.
Is this a quotation?
No, it is a guide. An exact price comes from a BOQ of the retrofit design; send us the design for one.
Tell us about the building.
Send drawings, photographs or earlier reports. An engineer will reply with what investigation is needed and a proposal.