A tilted building is not automatically about to collapse, but a tilt that appeared suddenly or is still increasing is one of the most serious warning signs a building can give. After the earthquake of 21 November 2025, RAJUK reported that at least 50 buildings in Dhaka had tilted or developed major cracks, sealed several of them and asked for Detailed Engineering Assessments. This article explains why buildings tilt, how engineers measure it, and how owners should respond.
Key figures
The 21 November 2025 earthquake in numbers
5.7
magnitude (BMD)
25 km
from Dhaka to the epicentre
50+
Dhaka buildings tilted or badly cracked (RAJUK)
10+
people killed
Sources: Bangladesh Meteorological Department, RAJUK, as reported by TBS and Prothom Alo, Nov 2025.
Why buildings tilt
Almost every tilt in Bangladesh starts in the ground, not in the frame. A building leans when one side of its foundation sinks more than the other. That uneven settlement has a few common causes:
- Soft or filled ground. Large parts of Dhaka, Narayanganj and Gazipur stand on low land raised with dredged sand or mixed fill. Fill keeps compressing for years, and it is rarely uniform across a plot.
- Earthquake shaking. Shaking packs loose sand more tightly, and saturated loose sand can briefly lose strength altogether (liquefaction). Either can let one side of a foundation drop.
- Overloaded foundations. Floors added years after construction, heavy rooftop tanks or a change to warehouse or factory use can push footings beyond what the soil carries evenly.
- Neighbouring work. A deep excavation or dewatering for a new basement next door can draw soil or water from under an older building.
- Leaking pipes and drains. Water washing fine soil out from under a footing for years can create voids on one side.
A tall, slender building on shallow footings amplifies the problem: a small difference in settlement at the base becomes a large movement at the roof.
Old tilt or new tilt: how engineers read a leaning building
Follow a five-storey building on filled ground from the first sign to the fix.
Old tilt or new tilt: the question that matters
Many buildings in Dhaka have leaned slightly for years and stopped moving long ago. Others started leaning after the earthquake, or are still moving. The two need completely different responses, and you cannot tell them apart by eye.
| Sign | Points to an old, stable tilt | Points to new or ongoing movement |
|---|---|---|
| Doors and windows | Have always stuck; frames adjusted long ago | Suddenly jam or swing open by themselves |
| Cracks | Old, dirty, painted over | Clean edges, new plaster cracking, cracks that grow |
| Gap to neighbour | Unchanged for years | Widening, or the buildings now touch |
| Floors | Slight slope residents know about | New slope, marbles roll, water ponds in new places |
| Utilities | Working | Pipes breaking, gas or water leaks at the base |
How engineers measure tilt
A proper tilt survey replaces impressions with numbers, and repeats them to see whether anything is changing.
- Verticality survey. A total station measures points on each corner of the building at several heights. From these the engineer calculates how far the top has moved relative to the base, and in which direction.
- Level survey of the floors. Levels taken across the ground floor and upper floors show the shape of the settlement, for example whether one corner or one whole side has dropped.
- Crack mapping. Every crack is recorded with its width, length and direction. The pattern tells the engineer how the building has moved.
- Monitoring. Survey targets and crack gauges are fixed to the building and read again after days and weeks. Movement that continues changes the urgency completely.
- Ground and foundation investigation. Boreholes beside the building and, where needed, a trial pit to expose a footing show what the building stands on.
When is a tilted building unsafe?
The engineer weighs four things together:
- Is it still moving? A stable tilt can often be lived with after checks; a moving one cannot.
- How large is it compared with the height? The same lean at the roof is far more serious on a six-storey building on shallow footings than on a two-storey one.
- What has it done to the frame? Cracks in columns, beams and their joints mean the structure is carrying forces it was not designed for.
- What is the cause? A cause that is still active, such as a leaking drain or excavation next door, has to be stopped first.
The answer is usually one of three: safe to use with monitoring, use restricted until stabilised, or vacate until stabilised or demolished.
What can be done
Monitoring and simple measures
For an old, stable tilt with no structural damage: regular monitoring, repairing leaking drains, removing heavy rooftop loads and keeping water away from the foundations.
Stabilising the foundation
For a tilt that is moving: underpinning the settling side, adding mini-piles or micro-piles beside existing footings, or tying separate footings together with ground beams so they move as one. The design follows a soil investigation and an assessment of the existing foundations.
Strengthening the frame
Where columns and beams have cracked, jacketing or CFRP restores their strength once the foundation movement has been stopped. Repairing the frame first is wasted money if the ground is still moving.
Correcting the tilt
In some cases a building can be partly brought back towards vertical by controlled jacking at the foundation or by controlled soil removal on the high side. It is specialist work with real risks, and not always worth the cost compared with stabilising the building where it is.
Demolition
When the tilt is large, still increasing and the frame is badly damaged, demolition may be the only safe option. A Detailed Engineering Assessment gives owners and authorities the evidence for that decision.
Self-check
How exposed is your building to earthquake damage?
Tick everything that is true for your building. This is a first screening, not an assessment.
Your result
Tick the items above to see your result.
If RAJUK has issued a notice
After the November 2025 earthquake RAJUK served notices on buildings it considered risky, sealed several and asked for Detailed Engineering Assessments. If your building has a notice, read exactly what it asks for and by when, keep a copy, and appoint a qualified engineering firm promptly. The assessment report is what lets the authority, the owners and any bank or buyer decide what happens next. See our guide to the Detailed Engineering Assessment.
A closer look at the causes on Dhaka's ground
Understanding the cause matters because the cure follows it. Engineers usually find one of four situations when they investigate a tilted building in and around Dhaka.
Shallow footings on recent fill
Many buildings of four to six storeys on the city's eastern and northern fringes stand on isolated footings placed in sand fill only a few years old. Fill placed by dredging is often loose, and its thickness varies across a plot because the original ground had ponds, ditches and paddy levels. When the building is loaded, or when an earthquake shakes the fill, the thicker side compresses more. The building rotates towards it. The give-away is a tilt in one direction with cracks concentrated on the opposite side's ground-floor walls.
Mixed foundations
Some buildings were started on footings and extended later on a different foundation, or have part of the building on piles and part on footings. The two parts settle differently and the building twists or cracks along the junction. A level survey of the ground floor usually shows a step at the line where the foundations change.
Overloaded footings
A building designed for four storeys that now carries seven, or a home converted into a store or garment unit, can push its footings past what the soil carries. Settlement is then larger under the most heavily loaded columns, usually the interior ones or those under water tanks and stairs.
Ground loss beside the building
A new basement next door, a collapsed drain or years of leaking water can remove soil from under one side. The tilt is then towards the excavation or the leak, and it often started after a specific event that neighbours remember.
What the measurements look like
Owners often ask how the engineer turns a survey into a decision. The surveyor gives the horizontal offset of the roof relative to the base at each corner, and the engineer expresses it as a ratio of the building's height, for example "1 in 200". The ground-floor levels give the differential settlement between columns, which is compared with the distance between them to get the angular distortion. These ratios are compared with limits used in foundation engineering for cracking of walls and for damage to the frame. Just as important is the trend: three or four readings a few weeks apart show whether the numbers are stable.
| What is measured | How | What it tells the engineer |
|---|---|---|
| Tilt of each corner | Total station on targets at roof and base | Direction and size of the lean |
| Floor levels | Precise levelling on each floor | Which columns have settled, and by how much |
| Crack widths | Crack gauges, tell-tales, photographs | Whether movement is continuing |
| Foundation size and depth | Trial pit beside a footing | Whether the footing matches the drawings and the load |
| Soil profile | Boreholes with SPT | How deep the fill or soft soil goes |
Living with a monitored building
Where the engineer concludes that the building can be used while it is monitored, a few simple rules keep occupants safe:
- Do not add load: no new floors, rooftop rooms, tanks or heavy storage.
- Keep water away from the foundations: repair drains, gutters and leaking pipes at once.
- Keep the monitoring targets and gauges undisturbed, and let the surveyor in on the agreed dates.
- Report any sudden change straight away: a door that jams, a new crack, a noise from the structure.
- Agree in advance what reading would trigger evacuation, so nobody has to decide in a panic.
How a stabilisation project runs
- Investigation: survey, monitoring, boreholes and a trial pit, usually over a few weeks.
- Design: the engineer chooses underpinning, mini-piles or tying the footings together, and designs any frame repairs.
- Temporary works: props and, if needed, protection to the neighbouring building.
- Foundation works: carried out in short sections so the building is never left unsupported.
- Monitoring during and after: readings continue until they show the building has stopped moving.
- Frame repairs: crack injection, jacketing or CFRP once the movement has stopped.
Throughout, the owner should keep the records: survey reports, photographs and the engineer's certificates. Banks, buyers and RAJUK will ask for them later.
Where to start
- Take the free Building Safety Self-Check to record what you see.
- Photograph the cracks, door frames and the gap to the neighbouring building, with the date.
- Book a visual assessment. If the tilt is new or moving, ask for monitoring and a foundation investigation straight away.
Read more on earthquake building safety, or contact our engineers with your photographs.
Topics:EarthquakeSettlementFoundationsDhakaBuilding safety
Frequently asked questions
How much tilt is too much for a building?
There is no single number that makes a building unsafe; the risk depends on the cause, whether the tilt is increasing, the height and the structure. Engineers compare the measured tilt with the building's height and with limits used for foundations and serviceability, and above all check whether it is still moving.
Can a tilted building be straightened?
Sometimes. Depending on the foundation and the soil, a building can be stabilised by underpinning or new piles, and in some cases partly corrected by controlled jacking or soil methods. Straightening is specialised and not always worth the cost; stopping further movement is the first goal.
Who decides if a tilted building must be vacated?
If RAJUK or the local authority has issued a notice, follow it. Otherwise the decision rests on an engineer's inspection. If you see a sudden or increasing tilt, jammed doors or cracks in columns, move people out first and get the inspection immediately.
Why did some buildings tilt in a moderate earthquake?
Shaking can compact loose or filled soil under one side of a building, or weaken a foundation that was already overloaded. Buildings on recently filled land, with shallow foundations or with floors added later were the most affected.
About Muhammad Sarowar Hossain
Founder & CEO, Prime Base Engineering, B.Sc. in Civil Engineering, PGDSCM-ISCEA. Muhammad Sarowar Hossain founded Prime Base Engineering and leads its structural assessment, retrofitting and construction work. He has worked on structural retrofitting of factories and industrial buildings across Bangladesh since 2017.